Project Schedule
A before photo and after rendering of the area in Downtown Pittsburgh that will be transformed into the new Gateway Center Subway Station. Under a contract with Port Authority, Light Motion Collaborative is designing the new station for the North Shore Connector.
 
View construction information about the project
 

North Shore Connector Time Line

Time Frame Progress
January 1995 Port Authority and SPC initiate Spine Line MIS/DEIS (Major Investment Study / Draft Environmental Impact Statement)
November 1995 New Allegheny County Commissioners elected
May 1996 Allegheny County Commissioners order Port Authority to stop the Spine Line MIS/DEIS
1996 City of Pittsburgh begins Pittsburgh Downtown Plan
July 1996 County Commissioners write letter Port Authority Board requesting consideration of a Golden Triangle - North Shore rail line
Fall 1997 City of Pittsburgh and SPC begin North Shore/CBD Transportation Corridor MIS
1998 Pittsburgh Downtown Plan completed. Includes recommendation for a Golden Triangle - North Shore rapid transit link
January 1999 Port Authority begins North Shore Connector DEIS
March 1999 North Shore/CBD Transportation Corridor MIS completed
October 1999 Port Authority presents draft DEIS to FTA at Region III
June 2000 North Shore Connector DEIS available for public review
June 2000 DEIS Public Hearing
August 2000 Port Authority Board selects the Gateway Alternative as the LPA
September 2000 Port Authority submits New Starts Criteria and request to enter into Preliminary Engineering
January 2001 FTA authorizes Port Authority to enter into Preliminary Engineering PE/FEIS begin
September 2001 Port Authority presents draft FEIS document to FTA in Pittsburgh
November 2001 New Starts Criteria Financial information submitted to FTA
May 2002 North Shore Connector FEIS available for public review
May 2002 Project Public Open House
July 2002 FTA issues ROD
October 2002 Transportation Systems User Benefit information submitted to FTA
April 2003 FTA approves entry into Final Design
February 2004 North Shore Connector one of five projects nationwide to be recommended for a Full Funding Grant Agreement
August 2005 Bids for tunnel section well above budget
December 2005 Environmental Report on Proposed Project Revision circulated for public review and comment
January 2006 Port Authority Board approves advancing the North Shore Connector with deferral of the Convention Center Line
February 2006 Second round of bids received
July 2006 Port Authority Board authorizes awarding of first contract
August 2007 Tunnel Boring Machine arrives in Pittsburgh
January 2008 Mining of the first tunnel begins at North Shore launch pit
April 2008 Gateway Station Shell Bid comes in almost 100% over budget
June 2008 Aerial Structure Bid comes in 50% over budget
July 2008 Tunnel Boring Machine arrives in receiving pit located under Stanwix Street
October 2008 Train Systems Bid comes in over 100% over budget
January 2009 Tunnel mining completed
January 2009 Port Authority announces updated project budget of $552.8 million, $117.8 million over FFGA
February 2009 American Recovery and Reinvestment Act of 2009 signed into law. Formula funds of $61.25 million for Port Authority included; $750 million in national New Starts and $1.5 billion in Competitive Surface Transportation Grants also included
February 2009 Train Systems & Elevator/Escalator Contracts awarded
December 2011 Scheduled completion of the North Shore Connector project by year's end.